HOUSING COMPLEX “Etalon city” “Tokyo” Towers

21 May 2018

Case 1
Concreting of vertical structures of the 25th floor has been completed.
Made masonry exterior walls to the 18th floor.
The installation of Windows on the 12th floor.
Installation of the subsystem and the thermal insulation of the facade of 35%.

Enclosure 2
The floor slab concreting of the 29th floor has been completed.
Made masonry exterior walls to the 26th floor.
Made masonry interior partitions to the 2nd floor.
The installation of Windows on the 13th floor.
The installation of the subsystem and the facade insulation of 45%.

Body 3
The concreting of the floor slab of the 31st floor has been completed.
Made masonry exterior walls to the 25th floor.
Made masonry interior partitions to the 6th floor.
The installation of Windows on the 15th floor.
The installation of the subsystem and the facade insulation of 45%.

Building 4
Work on the monolithic frame is completed.
Made masonry exterior walls to the 31st floor.
Made masonry interior partitions to the 23rd floor.
The installation of Windows on the 16th floor.
The installation of the subsystem and facade insulation 80%.
The installation of stained glass Windows of aluminum loggias of the facade of 70%.

Building 5
Work on the monolithic frame is completed.
Made masonry exterior walls to the 31st floor.
Made masonry interior partitions to the 30th floor.
The installation of Windows on the 21st floor.
Installation of subsystems and the façade insulation 90%.
The installation of stained glass Windows of aluminum loggias of the facade of 70%.

Building 6
Work on the monolithic frame is completed.
Masonry exterior walls made.
Made masonry interior partitions to the 18th floor.
The installation of Windows on the 12th floor.
The installation of the subsystem and facade insulation 80%.
The installation of stained glass Windows of aluminum loggias of the facade of 70%.

Towers 1,2,3,4,5,6
Started installation of risers of water supply, heating, ventilation.
In the area of the 1st, 2nd tower began to improve (performed concreting under the road).